An RF amplifier factory acceptance test assigns equipment provision, suitability checks, execution, witnessing and acceptance before the test date. RF amplifier production testing explains production coverage and traceability; the contractual FAT still needs its own configuration-specific responsibility matrix.

Name the supplied and external items

List the DUT and each source, load, supply, cooler, controller, fixture and instrument with provider, revision and applicable calibration. Compare requested files and tests with the factory testing and documentation scope before treating them as agreed deliverables.

Fasteners and mounting holes on an amplifier module baseplate.

Assign every acceptance step

Give each RF test-plan row its requirement, method, conditions and criterion. The FAT adds the parties who provide and confirm the setup, execute, witness if required, retain the report and approve deviations or acceptance. One party’s ownership of the equipment does not answer all those roles.

Two engineers examine an amplifier module together at a workbench.

Agree deviations and release

Define how unavailable customer equipment, an out-of-limit result, or a configuration change is handled. A substituted setup needs an accepted explanation of equivalence or a limitation on the conclusion. Preserve raw results and the disposition of deviations.

An amplifier module in a separate inspection tray.

Assign FAT responsibility before the test date

Enter named parties for each separate role in the same test row. Do not leave “customer” or “supplier” as a catch-all assignment where the actual decision role is different.

FAT rowProvide equipmentConfirm suitabilityExecute / witnessApprove and retain
Power/coolingName supply/cooling providerName reviewer of limits and measurement boundaryName operator and required witnessAcceptance owner; actual-condition record
Signal/load pathName source/load/fixture providerPath reviewer uses the RF test-bench recordName RF test operator and witnessAcceptance owner; waveform and corrections
Control/statusName host/controller providerInterface owner confirms command/state versionName behavior-test performer and witnessAcceptance owner; observed transitions
Results/deviationsReport owner provides filesReviewer checks unit/requirement linkagePerformer preserves raw and repeat resultsNamed deviation approver and final accepting authority

If the required customer load is absent, mark the dependent row “not performed: prerequisite unavailable.” The named suitability reviewer and deviation approver must agree any substitute and its conclusion boundary before execution. Keep “performed: criterion not met” separate, with its actual result and retest disposition.

The final FAT package should identify the tested configuration and exactly what was accepted. The integration handoff sequence supplies prerequisites; the quote comparison checks whether the agreed test and document scope is actually included in the purchase.

For an amplifier procurement, attach the FAT responsibility matrix to the CorelixRF inquiry and distinguish requested checks from agreed supplier deliverables. Identify customer-furnished sources, loads and controllers so the quoted test boundary can be reviewed. Use the RF integration support route to define the hardware interfaces, supplied scope and records needed for the proposed installation.

Provide the FAT responsibility matrix, exact RF configuration, and power, control, thermal, and test deliverables to be agreed.

Discuss RF FAT Responsibilities