An RF amplifier factory acceptance test assigns equipment provision, suitability checks, execution, witnessing and acceptance before the test date. RF amplifier production testing explains production coverage and traceability; the contractual FAT still needs its own configuration-specific responsibility matrix.
Name the supplied and external items
List the DUT and each source, load, supply, cooler, controller, fixture and instrument with provider, revision and applicable calibration. Compare requested files and tests with the factory testing and documentation scope before treating them as agreed deliverables.

Assign every acceptance step
Give each RF test-plan row its requirement, method, conditions and criterion. The FAT adds the parties who provide and confirm the setup, execute, witness if required, retain the report and approve deviations or acceptance. One party’s ownership of the equipment does not answer all those roles.

Agree deviations and release
Define how unavailable customer equipment, an out-of-limit result, or a configuration change is handled. A substituted setup needs an accepted explanation of equivalence or a limitation on the conclusion. Preserve raw results and the disposition of deviations.

Assign FAT responsibility before the test date
Enter named parties for each separate role in the same test row. Do not leave “customer” or “supplier” as a catch-all assignment where the actual decision role is different.
| FAT row | Provide equipment | Confirm suitability | Execute / witness | Approve and retain |
|---|---|---|---|---|
| Power/cooling | Name supply/cooling provider | Name reviewer of limits and measurement boundary | Name operator and required witness | Acceptance owner; actual-condition record |
| Signal/load path | Name source/load/fixture provider | Path reviewer uses the RF test-bench record | Name RF test operator and witness | Acceptance owner; waveform and corrections |
| Control/status | Name host/controller provider | Interface owner confirms command/state version | Name behavior-test performer and witness | Acceptance owner; observed transitions |
| Results/deviations | Report owner provides files | Reviewer checks unit/requirement linkage | Performer preserves raw and repeat results | Named deviation approver and final accepting authority |
If the required customer load is absent, mark the dependent row “not performed: prerequisite unavailable.” The named suitability reviewer and deviation approver must agree any substitute and its conclusion boundary before execution. Keep “performed: criterion not met” separate, with its actual result and retest disposition.
The final FAT package should identify the tested configuration and exactly what was accepted. The integration handoff sequence supplies prerequisites; the quote comparison checks whether the agreed test and document scope is actually included in the purchase.
For an amplifier procurement, attach the FAT responsibility matrix to the CorelixRF inquiry and distinguish requested checks from agreed supplier deliverables. Identify customer-furnished sources, loads and controllers so the quoted test boundary can be reviewed. Use the RF integration support route to define the hardware interfaces, supplied scope and records needed for the proposed installation.
Provide the FAT responsibility matrix, exact RF configuration, and power, control, thermal, and test deliverables to be agreed.
Discuss RF FAT Responsibilities